Industrial Air Technology
KG Steel
KG Steel No.5 Color Coating Line ventilation System
Target Space | No.5 Color Coating Line |
---|---|
Location | Dangjin, Korea |
Project Type | EPC |
Contract Date | 2021. 01 |
Installation Period | 90days |
Customer's Needs | 1. Air supply (full construction progress)
- Use outdoor air (about 2m space between the factory building and the raw material storeroom) - Air supply fan : 1st floor installation - duct : 1st floor upper installation - Air supply location: 1st and 3rd floor coater room, including fabrication warehouse - Air-conditioning: Heating coil (steam used in steelworks: 100℃, 7kg/hr, 20~25℃ air supply) 2. Exhaust - Coater exhaust fan: 700 N㎥/min (distance to exhaust fan about 30-35m) - The exhaust air velocity in the coater is 0.5 m/sec or higher in accordance with the Safety and Health Act - Duct construction is carried out to the confluence of the 1st and 3rd floors 3. Others - No. 5 CCL: Separation of coating rooms and other places with reinforced glass |
Guarantee & Result Value |
---|